RL 8: Retaining walls - Ridge

Retaining walls

Ridge Lines

This overview explains the principal types of retaining wall, the engineering principles upon which they rely, common construction methods and the mechanisms by which failures occur. It also highlights the complex interaction between geotechnical engineers, structural engineers, temporary works designers and contractors, helping practitioners identify potential causes of failure, allocate responsibility and instruct experts more effectively.

Retaining Walls

Summary of key facts, correct at time of writing.

Overview

Any form of structure that requires significant excavation to cater for a step in ground level, either temporary or permanent, may require a retaining wall in some form. Exceptions are rare and generally occur where excavations are carried out in unfractured rock, or a site has enough surrounding space to allow a battered slope. A retaining wall is a structure embedded into the ground, which maintains a given height of ground behind it. A retaining wall that retains water on the outside and allows dry working space within is called a caisson and is outside the scope of this note.

There are many forms of retaining wall and numerous variables that determine the type and configuration of the wall, including:

  • the depth of excavation;
  • whether the construction process within the excavation has space for propping;
  • local ground conditions and level of water table;
  • the amount of acceptable ground movement, relevant to nearby buildings, roads or utilities;
  • the loading on the wall itself as well as the ground behind it;
  • local availability of materials and skilled contractors;
  • appearance and long-term maintenance requirements, etc.

Design Guidance

BS 8002: 2015 provides recommendations for design and construction of retaining walls in accordance with Eurocode 7 for Geotechnical Design. Numerous other guidance documents exist that cover specific types of retaining walls, as well as relevant temporary works guidance, such as:

  • BS 8002:2015 – Code of practice for earth retaining structures, BSI, 2015;
  • BS 8004:2015 – Code of practice for foundations, BSI, 2020;
  • BS 8006:2010 – Code of practice for strengthened/reinforced soils. Soil nail design, BSI, 2010;
  • C516 Modular gravity retaining walls: design guidance, Ciria, 2000;
  • C760 Guidance on embedded retaining wall design, Ciria, 2017;
  • PAS 8812:2016, Temporary works – application of European Standards in design – guide, BSI, 2016;
  • Specification for Piling and Embedded Retaining Walls, 3rd, ed., ICE, 2016.

There are two main types of retaining walls, embedded walls and gravity walls. Let’s look at these in turn.

Embedded retaining walls

Embedded retaining walls generally work by virtue of the structure being embedded into the ground, with the structure resisting the horizontal forces of the ground in bending. The major advantage of embedded retaining walls is that they can be installed from ground level and thus provide a safe support structure prior to excavation. Forms of embedded wall include:

  • Cantilever walls – generally a vertical wall embedded in the soil to provide a fixed base and resists soil pressure by bending. Suitable for shallow or modest excavations.
  • Propped walls – similar to cantilever in format but include horizontal or raking props near the top of the wall which act to reduce ground movements and forces in the wall itself, enabling a more economical structure and/or a deeper excavation.
  • Tied – similar to the propped wall but the top of the wall is tied or anchored back into the ground behind the wall. Difficult in urban locations due to adjacent ownership issues.
  • Combination – for deeper excavations it is possible to combine anchors and props to avoid a very congested excavation.

Specific structures used as embedded retaining walls include:

  • Contiguous bored piles, most commonly installed with a continuous flight auger (CFA) type piles, which are formed by drilling an auger into the ground, which is then slowly withdrawn to extract the soil. Concrete is pumped down the centre of the auger to backfill the hole with concrete as the auger is withdrawn. Finally, a reinforcement cage is dropped through the wet concrete to reinforce the pile. These are economical and typically used in basements where risk of water ingress is low.
  • Steel sheet piles comprise a series of interlocking steel plates which are pre-formed in a U or Z to add stiffness. These can be installed using hammer impact, vibration or hydraulically pushed into most types of ground except dense gravels and rock. These can be temporarily waterproofed at the joint to provide an effective water barrier in submerged soils, but are typically more flexible than concrete piles.
  • Secant piles walls are formed by first installing a soft (typically unreinforced) pile at set spacings, then going back to the start of the run and drilling hard (reinforced) or primary piles which intersect with the previously installed soft piles, which are formed of a weaker concrete mix. These are especially useful in ground with a high or mobile water table. Hard/Hard piles can be used where the retaining wall design dictates, (higher forces, greater height of retained soil), but this requires a stonger auger for cutting the second row of piles.
  • Diaphragm walls are constructed by excavating vertical slots in the ground with a special cutting tool or ‘grab’. The slots in the ground are temporarily filled with a thick slurry to avoid collapse. These slots are then filled with concrete, simultaneously displacing the slurry which is pumped out, and finally a reinforcement cage is dropped into the wet concrete to form a reinforced concrete wall. Adjacent sections of wall are then formed in the same way. This provides a high quality wall but at a high cost, so is typically used in deep basements.

Gravity walls

Gravity retaining walls generally rely on the weight of the structure, sometimes combined with the weight of the ground itself, to prevent sliding and overturning. These are generally more economical than embedded walls, but the disadvantage of gravity walls is that they can only be installed after significant excavation has been completed, meaning significant backfilling to reinstate the ground at the higher level. Types include:

  • Mass concrete gravity walls – a mass concrete or masonry structure that relies solely on weight of structure to resist sliding and overturning.
  • Reinforced Concrete gravity walls – utilizes the mass of concrete combined with the weight of soil on top of the base slab to resist sliding and overturning, with extra strength to the wall from the reinforcing steel allowing a slimmer concrete section to the traditional mass concrete gravity wall.
  • Gabions or Cribs – Wire mesh boxes or frames filled with stones or selected backfill material to resist sliding and overturning, generally raking back to reduce ground pressure on the back of the wall.
  • Reinforced soil – granular soils can be reinforced with multiple layers of plastic mesh or geotextiles and compacted to form a stable slope with an appreciable gradient. A similar approach can be carried out with soil nailing into the sloped ground.

Design principles

Regardless of the type of wall, in all cases there is a horizontal force on the wall from the retained ground, called the ‘active’ pressure. For an embedded wall, this is resisted by the structure in bending. The ground on the excavated side of the wall, which helps to embed the wall at the base, also resists the active pressure with an opposing force called the ‘passive’ pressure. For a gravity type of wall, horizontal sliding and overturning are resisted by friction under the base of the structure and its mass respectively.

Other loads can also affect retaining walls. Water in the soil also adds to the horizontal pressure on the back of the wall,

as does any imposed load on the ground at the top of the wall, such as traffic or adjacent buildings. Earthquake loads can also be applicable.

The passive resistance at the base of the wall is often critical, so allowance is typically made for additional unplanned excavation in front of the wall, effectively assuming a reduced passive pressure as a conservative design measure.

Construction method

Construction methodology for retaining walls and basements can be varied and exceedingly complex, especially on urban sites where adjacent buildings or underground structures can pose constraints. As outlined above, gravity walls typically require the excavation to be done first, then construction of the structure, followed by backfilling to reinstate the ground. On a site with ample space around the excavation, this is an economical process. Embedded retaining walls are more appropriate for deeper excavations, or constrained sites where retaining is required close to the boundary, and result in more complex sequences of construction, some of which we shall outline here.

Open excavation is the simplest form of basement construction using cantilever retaining walls as well as some propped walls. The excavation can be safely done after the piles are installed, providing maximum workspace to form the new structure inside the basement box. The simplest and most economical form of embedded wall construction.  This is typically only suitable in shallow basement, where the wall can be designed without additional propping.

Bottom-up construction is a variant of open excavation which is applicable to deeper basements requiring propping at multiple levels. As excavation proceeds, additional levels of props are added to prevent significant deflections. Once, the base level is reached, construction of the structure can commence, although this is often complicated by needing to construct around props, which are removed after the structure at that level is in place.

Top-down construction is a particularly complex sequence, used on urban sites to minimise risk of ground movements and increase the speed of construction. Piles are installed first, followed by the ground floor slab, which effectively works as a prop in this instance. The piles inside the building footprint also have an embedded steel column within, which will form the final column of the structure. Holes are left in the slabs to allow removal of material, which is excavated by small diggers and moved to the hole location where is it hauled out by a grab. Then the first level basement structure can be formed, using the internal steel columns as supports. This sequence is repeated until the basement level is complete. The structure above ground can also be constructed simultaneously, allowing for a fast construction process for a building with deep basements.

Ground movements

One of the biggest issues with retaining walls is the risk of ground movement, in particular with embedded walls. The ground around the excavation can subside due to the horizontal deflection of the wall. This in turn can cause foundation movement and structural damage to adjacent buildings or surrounding below ground features (sewers and tunnels). An increase in the amount of propping or the adoption of a top-down construction sequence can reduce these movements and risk of damage, but at a cost. So, basement construction tends to be a balance of cost and time against the choice of sequence and amount of propping.